Estimator Application‎ > ‎Tutorial‎ > ‎

31. Update prices from project to default cost type library

As you can you see, is the price for a dozer 35.28 / h. Change that value to 20.

Now lets look in the default cost type library what price a dozer costs, probably 35.28. Select in the menu bar: System > Default cost type library.

As you can see, the value for a dozer is 35.28. We want this value to be the value from the cost type library. Select the cell or another cell from the same row.

To update the dozer price to 20, click on the Update button.

As you can see, the price of dozer is updated to 20. Select in the menu bar: System > Estimator.